City of Saline Construction Update: Downtown Parking, Cemetery and West Bennett Street

 10/06/2017 - 15:43

The following construction updates were provided by City Manager Todd Campbell



Concrete curb and sidewalk replacement work was competed on October 5th.

Concrete curing time occurs over the weekend and the planned activities for the week of October 9th are:

  • Contractor is scheduled to begin asphalt removals on October 9th – 10th
  • October 11th install underdrains, perform subbase undercuts, place limestone base, and complete site grading
  • Asphalt paving is scheduled for October 17th – 18th.
  • Pavement markings and bumper placement is scheduled for October 19th – 20th.
  • Parking lot #4 is currently scheduled to re-open by the end of the day on October 20th.



  • The contractor is scheduled to begin the pavement milling/removal and re-paving project October 23rd, with a completion date of November 3rd.  



  • The contractor is scheduled to begin and complete the milling and re-paving of current patched sections of W. Bennett Street either the week of October 16th or October 23rd.


Note:  The above schedules are of course weather dependent.

Residents and stakeholders are encouraged to contact the City Engineer (734-429-8296 ext 2222) or the DPW (734-429-5624 ext 260) with questions/concerns.