A progress meeting was held with the contractor on August 30. The contractor has executed purchase orders with their suppliers, and the procurement of necessary equipment is underway. Work has started including excavation and concrete for the foundations for the odor control and generator. Construction of much of the duct work is scheduled to begin in October.
The contractor is on track to have the major odor control equipment at the WWTP operational in spring 2019. Some smaller equipment, such as the odor control equipment at the Southside Pump Station (located on Saline-Milan Road adjacent to Wilderness Park), may be functional in November dependent upon equipment delivery and weather.
Please contact Steve Wyzgoski, WWTP/WTP Superintendent with questions at 734.944.2003.
(Issued by City Manager Todd Campbell)