City of Saline Manager Todd Campbell released the following details about the city's ongoing paving projects.
PARKING LOT #4
Asphalt removals are complete. The underdrain installation, subbase undercuts, limestone base placement and site grading will be completed Friday, October 13th.
The planned activities for the week of October 16th include:
Base preparation and tack coat October 16th.
Asphalt paving is scheduled for October 17th – 18th.
Pavement markings and bumper placement is scheduled for October 19th – 20th.
Parking lot #4 is currently scheduled to re-open by the end of the day on October 20th.
OAKWOOD CEMETERY PAVING PROJECT
The contractor is scheduled to begin the pavement milling/removal and re-paving project October 23rd, with a completion date of November 3rd.
BENNETT STREET PATCHING
The contractor is scheduled to begin and complete the milling and re-paving of current patched sections of W. Bennett Street on Saturday, October 14th.
Note: The above schedules are of course weather dependent.
Residents and stakeholders are encouraged to contact the City Engineer (734-429-8296 ext 2222) or the DPW (734-429-5624 ext 260) with questions/concerns.